Use this guide as a reference when filing lien and bond claim notices for the month of October. If you have any questions about the lien and bond claim process, don’t hesitate to reach out to any member of the Gray Reed Construction Practice Group. Be sure to subscribe to the Texas Construction Law Blog to automatically receive our monthly lien and bond guides, as well as other content related to legal issues impacting the construction industry.

ien and Bond Claim Notices and Filings Required by:October 15, 2024

Texas Property Code Chapter 53
Notice of Intent to Lien for Subs/Suppliers of All Tiers for Work/Materials Furnished During:  July 2024
Liens Filed by Original Contractors and Subs/Suppliers of All Tiers for Work/Materials Furnished During:  June 2024

Texas Government Code Chapter 2253
Notice of Unpaid Claim for Subs/Suppliers of All Tiers for Work/Materials to GC Furnished During:  August 2024
Notice of Unpaid Claim for Subs/Suppliers of All Tiers for Work/Materials to GC and Surety Furnished During:  July 2024

Residential
Notice of Intent to Lien for Subs/Suppliers of All Tiers for Work/Materials Furnished During:August 2024
Liens Filed by Original Contractors and Subs/Suppliers of All Tiers for Work/Materials Furnished During:July 2024